Medical Training Application ServiceProject Milestone Plan
Oct 05 Scope/Set up Project (Stage 0)

Nov 05 – Initiate Project (Stage 1)

  • Set up Project Board
  • Agree Project Brief

Dec 05 – Agree Requirements (Stage 2)

Jan 06 – Procurement/Approvals (Stage 3)

  • Procurement plan
  • Agreed Requirement

Feb 06

  • Funding Agreed
  • Issue EOI request to suppliers

March 06

  • Agree supplier list
  • Business Approval
  • Issue request to tender
  • Q&A Workshop
  • Evaluation starts

April 06

  • Supplier presentations
  • Evaluation panel recommendation
  • Award contract

April/Sept – Set up service (Stage 4)

  • June 06 Document user interface

Sept – Service roll out and training (Stage 5)

Oct 06 – F1 Service live

Feb 07 – Specialty, F2 and GP Service live

Jun 07 – Handover service & close (Stage 6)

Mike ClementMTAS Project Manager 07 March 2006

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s